Master Plan Amendment #2

Whitworth Water District No. 2 is preparing Master Plan Amendment #2 to update its plans for providing reliable drinking water service. The District invites customers and interested community members to learn about the proposed Amendment and provide comments at a public meeting on November 5, 2026.

Project Need:

The District periodically reviews its water system needs and planned improvements to support dependable service for existing and future customers. This Amendment reviews options to replace aging critical facilities and is necessary for the District to be eligible for funding and to implement the selected improvements.

Project Description:

Amendment No. 2 updates Chapter 8 of the 2018 Comprehensive Water System Plan (2018 WSP). The District is preparing this targeted amendment to add high-priority projects to the 10-year Capital Improvement Program (CIP) and support near-term funding applications before the next comprehensive WSP update.  The following priority projects are described herein:

  1. Zone 2 – Replacement of Reservoir 2, improvements along Wall Street, and transmission improvements along either Graves Road or Hawthorne Road.
  2. Zone 3 – Replacement of Reservoir 3.
  3. Zone 8 – Replacement of the Midway Reservoir and reconstruction of the Midway Booster Station, both at the existing MacDonald Reservoir site.

This Amendment incorporates the capital projects described above. All other portions of the 2018 WSP and Amendment No. 1 remain in effect.  This Amendment includes the District’s updated 10-year CIP to reflect current priorities, planning-level costs, and anticipated implementation timing.

The Amendment establishes the planning framework for these improvements. Individual projects will proceed through applicable design, permitting, funding, and construction steps.

Expected Outcomes:

Implementation of improvements described within the Amendment will improve system reliability and operating efficiency.

Current Status:

The proposed Amendment is being prepared for public review. The District will present an overview and provide an opportunity for questions and comments at the following public meeting:

Thursday, November 5, 2026

2:00 p.m. Pacific Time

Location:  Whitworth Water District No. 2 Office

17401 N. Newport Road, Mead, WA 99021

Review the proposed Amendment: https://welchcomer.egnyte.com/dl/kRcjG77R9r4K

Submit questions or comments: Tim Murrell, General Manager

E-mail: tim@whitworthwater.com

Phone (509) 466-0550

Anticipated Schedule:

November 5, 2026

  • Public meeting
  • Review of public comments
  • District consideration of Amendment adoption

Washington State Department of Health review and approval: November

Project Overview Map:

Ardmore Waterline Replacement

Whitworth Water District No. 2 is replacing aging water mains and services on W Ardmore Dr. This work will improve system reliability and long-term service to local properties.

Project Need: The District has discovered multiple leaks over the past 5 years on 350 feet of existing 1960s steel water main in Ardmore Drive between 1520 W Ardmore and W Lawrence Drive. Replacing these pipes addresses those leaks, reduces District maintenance costs, and improves system reliability.

What to Expect:

Schedule

Work on W Ardmore Drive and W Lawrence Drive began September 28th and project completion is anticipated in late October.

Water Outages

Localized temporary water service interruptions are expected during construction. These will be short-duration, and we are making every effort to minimize their frequency and duration. Notice (via door hangers) will be provided in advance of planned service impacts.

Roadway/Access Impacts

  • Temporary road closures or detours may occur.
  • Driveways may be blocked for short periods.

For planned blockages, we will notify residents in advance (via door hanger), so that you may plan ahead to park outside the active construction zone.

Surface Impacts

The majority of the project impacts the existing road surface.  However, small portions of work may disturb private surface improvements located within the public rights of way or easements.  We are making every effort to minimize disruption and restore these improvements as closely as possible to their original condition.  Additional details are provided below.

Surface Impacts and Restoration: 

Hardscape (includes driveways, retaining walls, and fencing)

We will repair or replace impacted hard surfaces (concrete, asphalt, gravel).

Lawn, Vegetation, and Tree Removals & Restoration

Disturbed lawns will be restored with sod or seed. Property owners will be responsible for watering and maintenance after installation.

We will preserve landscaping where possible. If removal is necessary, the ground will be restored, but plant replacement will be the property owner’s responsibility.

Sprinkler Systems

Damaged sprinkler lines or heads will be repaired. If issues are noticed after construction, please contact us and we will address them promptly.

Minihdoka Waterline Improvements

Whitworth Water District No. 2 is replacing aging water mains and services on W Koda Ct, Koda Trail, and N Minihdoka Trail. This work will improve system reliability and long-term service to local properties.

What to Expect:

Schedule

Update (10/20/26): Paving is scheduled for Wednesday 10/28. Work in the Mill/Addison intersection is anticipated to occur over a 3-5 day period in early November. Project completion is anticipated in mid-November.

Roadway/Access Impacts

  • Temporary road closures or detours may occur.
  • Driveways may be blocked for short periods.

For planned blockages, we will notify you in advance (via door hanger), so that you may plan ahead to park outside the active construction zone.

Surface Impacts

The majority of the project will impact the existing road surface. However, portions of work may disturb private surface improvements located within the public rights of way or easements. We will make every effort to minimize disruption and restore these improvements as closely as possible to their original condition. Additional details are provided below.

Surface Impacts and Restoration:

Hardscape (includes driveways, retaining walls, and fencing)
We will repair or replace impacted hard surfaces (concrete, asphalt, gravel) and reinstall affected walls and fences. You may choose to remove items in advance if preferred.

Lawn, Vegetation, and Tree Removals & Restoration
Disturbed lawns will be restored with sod or seed. Property owners will be responsible for watering and maintenance after installation.
We will preserve landscaping where possible. If removal is necessary, the ground will be restored, but plant replacement will be the property owner’s responsibility.

Sprinkler Systems
Damaged sprinkler lines or heads will be repaired. If issues are noticed after construction, please contact us and we will address them promptly.

Project Name: Well 3E

Tentative Construction Window- Ongoing through 2026

Project Need:  The District requires additional source of water supply to support peak summer (irrigation season) demands in the service area north of the Little Spokane River.  Long-term sustainability concerns are present in the Little Spokane River Aquifer north of the Little Spokane River.  Thus, the District has been working to minimize pumping of that Aquifer by developing additional well sources within the more prolific Spokane Valley Rathdrum Prairie Aquifer.

Project Description:  This project includes the drilling of a new 20-inch diameter well (completed in 2025), construction of a new well building and installation of a new pump and motor capable of providing 6,500 gallons per minute to the system.  This project is located on an existing well site owned by the District near Hastings and Mayfair Road.

Schedule:

Update: Construction has resumed now that evacuation zones for fires in the area have been lifted. Construction is anticipated to conclude in mid-December 2026.

Expected Outcomes:  Preservation of the Little Spokane River Aquifer resource while maintaining the existing reliable and high level of water service to the District’s customers located north of the Little Spokane River.

Current Status:  Construction of the new well building and installation of new pump and motor was awarded to D.W. Excavating.

Anticipated Schedule:  Construction is underway and is expected to be completed by the end of 2026 with completion by the end of the year.

Project Overview Map:

Funding: The District received a DOE Streamflow Restoration Grant of $1,519,000 for the Little Spokane River Water Resiliency Project, which included design and construction for Well 3E. This funding covers approximately 55% of the total Well 3E project cost, with the remainder of the funding coming from District reserves.

Hatch 2 Reservoir

Tentative Construction Window: This project is in the early design phase and the District is working to secure funding for construction in the 2026 – 2028 timeframe

Project Need:  The District’s existing Hatch Reservoir has insufficient storage volume to support peak hour demands and fire flow while maintaining adequate system pressure.

Project Description:  The District plans to construct a new 1 million gallon elevated storage tank east of Hatch Road and north of Bidwell Park.

Expected Outcomes:  Improved water service reliability and fire flow in the service area generally located north of Midway on either side of Hatch Road.

Current Status:  This project is in the design phase. The District has secured construction loan funding for construction in the 2027 – 2029 timeframe.

Anticipated Schedule:  Design is ongoing, with anticipated design completion in late 2026. Construction is anticipated to last between 8 and 15 months. Construction start dates are not yet known.

Project Overview Map:

Funding: Project design utilizes District funds. For construction, the District received notice of award for a $14.9 million Drinking Water State Revolving Fund loan for the Hatch 2 Reservoir. This loan amount is anticipated to cover the project construction cost.

Minihdoka Trail Water Main Replacement

Tentative Construction Window: June 2026 – October 2026

Project Need:  The existing waterlines in the Minihdoka/Koda Trail areas are leaking and showing signs of failure.

Project Description:  Replace approximately 3,500 lineal feet of failing steel and asbestos cement pipe.  A new 8 inch main line feed will extend from Dartford Road along Minihdoka Trail with a Pressure Reducing Valve Vault at the intersection with Koda.  A 4 inch main will extend along Koda Ct while a 6 inch main will extend along Koda Trail.

Expected Outcomes:  Improved water service reliability and fire flow.

Current Status:  Design and bidding are complete, and a construction contract has been awarded to Inland Infrastructure.

Anticipated Schedule:  Inland Infrastructure plans to construct the project from July 2026 – October 2026. Waiting for a July start helps reduce impacts related to seasonal groundwater in the area.

Project Overview Maps:

Funding: Design and construction are funded locally by the District.

Little Spokane River Water Supply Resiliency Project

Whitworth Water District (District) is the largest water purveyor within unincorporated Spokane County. The District provides water service to approximately 11,000 connections accounting for approximately 35,000 residents. The District’s current retail service area is highlighted in tan on the above map.

District’s Little Spokane River Water Supply Resiliency Project:

The District’s Little Spokane River Water Supply Resiliency Project (Project) encompasses two new high production wells (one of which is already constructed), and four and a half miles of 24” pipeline. The Project is anticipated to $14 million dollars.

The Project will effectively bridge the infrastructure and water supply gap between two groundwater sources: the Spokane Valley Rathdrum Prairie aquifer (SVRP); and the Little Spokane River aquifer (LSR). The SVRP is considered by many to be one of the most prolific aquifers in the world, while withdrawals from the LSR more directly, and negatively, impact stream flows of the Little Spokane river leading to increased water rights issues and the potential for adverse ecological impacts.

Demands in the Little Spokane River Aquifer:

During the District’s Water System Planning process in 2018, it was determined that additional District source capacity was required to support future growth within the LSR. The most cost effective and timely approach would have been for the District to construct additional wells in the Little Spokane river aquifer. Given the Hirst decision and resulting RCW 90.94, the District decided to play a leadership role and avoid further increasing Little Spokane river aquifer deficits in an already taxed and fragile watershed system.

Instead of increasing impacts to the LSR, the District developed a plan to drill a series of wells and transport that supply through new transmission lines from the SVRP up to the service area of the LSR. To date, the District has invested over $7.3 million toward these improvements (see map above), which have included:

  1. Acquisition of property for three new groundwater wells to be developed in Spokane Valley Rathdrum Prairie aquifer for use in WRIA 55.
  2. 9,500 feet of 24-inch transmission main (Phase I) connecting District WRIA 57 wells to its WRIA55 service area.
  3. Development and activation of District Well 3D (4,300 gallons per minute).

Benefits to Spokane County and the LSR:

This project is in direct alignment with Spokane County’s Comprehensive Plan – Capital Facilities and Utilities Goals and Policies.

A large portion of the Little Spokane River aquifer area within Spokane County is located within the boundary of the District’s retail or future service areas. RCW 90.94 does not require water offsets nor monitoring by Spokane County so long as new development is connected to a municipal water purveyor. As a means to provide necessary long-term water supply to the LSR, it is critical that the District’s Little Spokane River Water Supply Resiliency Project is completed.