Minihdoka Trail Water Main Replacement

Tentative Construction Window: June 2026 – October 2026

Project Need:  The existing waterlines in the Minihdoka/Koda Trail areas are leaking and showing signs of failure.

Project Description:  Replace approximately 3,500 lineal feet of failing steel and asbestos cement pipe.  A new 8 inch main line feed will extend from Dartford Road along Minihdoka Trail with a Pressure Reducing Valve Vault at the intersection with Koda.  A 4 inch main will extend along Koda Ct while a 6 inch main will extend along Koda Trail.

Expected Outcomes:  Improved water service reliability and fire flow.

Current Status:  Design and bidding are complete, and a construction contract has been awarded to Inland Infrastructure.

Anticipated Schedule:  Inland Infrastructure plans to construct the project from July 2026 – October 2026. Waiting for a July start helps reduce impacts related to seasonal groundwater in the area.

Project Overview Maps:

Funding: Design and construction are funded locally by the District.