Water Service Application and Agreement

RESIDENTIAL WATER SERVICE APPLICATION AND AGREEMENT

Anyone seeking new residential water service from Whitworth Water District, or changes to existing service, must first submit a completed Residential Water Service Application and Agreement (click here.). Note, this is only for people seeking new residential water service, not a tenant or a buyer of an existing property currently connected to Whitworth Water District.  

A completed and received Application does not constitute a right to water service.  District staff will review completed Application and contact applicant once a determination is made.  If approved, applicant agrees to pay all District required charges specific to the new water service at the fees established by the District at time of service.  Visit www.whitworthwater.com for current general facilities charge, rate schedule, miscellaneous charges, and labor and equipment rates.

Please direct any questions to operations@whitworthwater.com or by calling the District offices at (509) 466-0550.

Standard Drawings

Specifications

I. GENERAL

The pages found herein are specifications and requirements for general installation of materials, mains and facilities to be located within the boundaries of the Whitworth Water District (District). These items are minimums only and may be expanded to cover any particular project.

The following list of items shall apply to any new construction or projects;

A. A Developers Agreement for Water Extension between the District and developer, builder, or contractor shall be signed prior to construction.

B. All mains will be looped including mains in cul-de-sacs. Any exceptions will have to be approved by the District’s General Manager, Operations Superintendent or Operations Supervisor (District Management). All mains that are allowed to dead-end will end with a fire hydrant. In cul-de-sacs where mains are less than 600′ long, a flushing hydrant may be installed in place of a hydrant but must be approved by the District Management.

C. Prior to significant construction as determined by the District Management, plans of proposed facilities are to be submitted in duplicate to the District for approval. Detail blowups of special items are to be included. Said plans must bear the seal of a professional engineer licensed in the State of Washington. One copy of the plans bearing the approval signature of the District’s Engineer, District Management or both will be returned to owner, and these approved plans must be on the job site at all times during construction. Exceptions to these plan requirements can only be granted by the Board of Commissioners per item L.

D. Maintenance manuals shall be given to Whitworth Water District for all equipment, buildings and controls.

E. The District’s Engineer and or District Management shall review and approve all plans prior to construction at the expense of the owner/developer. A minimum of fifteen (15) days shall be allowed for this review process.

F. The owner/developer shall be responsible for obtaining plan approval or clearance from the Washington State Department of Health for his/her proposal at District’s request.

G. The Maintenance Superintendent or his authorized representative shall inspect all construction work at the expense of the owner/developer. It shall be incumbent upon the owner/developer to coordinate his/her construction activities and scheduling with the District Superintendent to avoid lost time.

H. District Operations Staff are the only individuals with the authority to open or close existing valves for construction purposes. The owner/developer shall notify the District at least 24 hours to his/her need to turn off water for construction purposes.

I. Obtaining necessary permits shall be the responsibility of the developer, builder, contractor or property owner affected.

J. Where franchises, easements or deeds to property are required, it shall be the responsibility of the affected party to provide same and submit appropriate documentation filing same with the County Auditor with a copy to the District prior to construction.

K. Fire protection requirements shall be approved by the appropriate agency prior to submission of plans to the District prior to construction.

L. Any requests for deviations or changes to these specifications shall be submitted in writing to the District thirty (30) days prior to construction. The Board of Commissioners will then consider the requested deviated change(s) at their regularly scheduled meeting and either approve or deny the request(s).

M. Equipment, tools, gauges, etc., required for tests shall be provided by the developer and/or contractor.

N. After construction is completed, complete and accurate “AS BUILT” drawings shall be submitted to the District. These drawings shall include dimensions from permanent reference points for all water lines, elbows, valves, and other such appurtenances in sufficient detail to facilitate future location, one to be drawn on reproducible mylar and one to be drawn on quality bond paper.

O. A set of road plans will need to be provided.

P. No water will be turned on until all paperwork, as required by the Water Service Agreement, is completed.

Q. The one-year Maintenance Bond will not begin until all paperwork has been turned into and approved by the District.

R. The owner/developer shall reimburse the District for all legal, engineering, and other incidental costs that the District may incur as a result of his/her proposal.

S. Whenever a group of homeowners joins together to put in a line extension or other mutually beneficial project, they shall appoint one person to act as liaison between the group and the District on the project.

II. SERVICES AND METERING THEREOF

A. GENERAL

1. Application for individual service will be made at the District office, including a legal description of the property to be served. A plat plan may also be required. The minimum size of the service will be determined by the District. Hook-up fees will be paid before installation will be made. Any other charges incidental to the extension of service lines to the applicant’s property will be paid by the applicant.

2. Meters shall be furnished and installed by the District in accordance with District policy at Owner’s expense.

3. Meters generally shall be installed inside houses or buildings unless otherwise approved by District Management. A minimum of two (2) feet of clearance shall be required for meter accessibility.

4. Service depth shall have four and one half (4.5) feet of minimum cover.

5. No services shall be made within three (3) feet of the end of any pipe, pipe joint or any coupling.

6. Backflow devices, when required, shall be installed according to the District’s Backflow Prevention Program. A minimum clearance of three (3) feet shall be required for access and maintenance of the appliance. All shall be installed after the metering devices.

7. No service shall be installed within the prescribed distance of a drain field as required per the Spokane Regional Health District. Where easements through property exist, a ten (10) foot clearance on each side will be required to the drain fields.

8. Bullhead taps, or multiple meteres on a single service line shall not be allowed on any services.

9. All copper connections shall be compression type fittings. All galvanized connections shall be threaded fittings.

10. Pressure regulators or pressure reducing valves are required where water pressure exceeds 80 PSI and are to be installed by the homeowner downstream of the meter.

11. All services shall be individually tapped to the distribution main or service main. NO DOMESTIC SERVICE(S), BE THEY TEMPORARY OR PERMANENT, WILL BE PLACED ON PRIVATE FIRE MAINS, PRIVATE FIRE SERVICES OR DISTRICT-OWNED TRANSMISSION MAINS.

B. SERVICE SIZE AND PARTS

1. Single family dwellings will be limited to a single one (1) inch service with a single one (1) inch meter, or three-quarter (3/4) inch meter.

2. For duplexes, each side to be a single service with one (1) inch service with a single one (1) inch meter, or three-quarter (3/4) inch meter.

3. Condominiums shall be designed on an individual basis. Approval must be obtained prior to authorization of service.

4. Services for three or more living units shall have a minimum two (2) inch service with a two (2) inch meter; however, each apartment house or apartment complex service shall be approved by District Management. For apartment complexes a single meter and backflow device is required for facility isolation.

5. Spacer requirements for plumbers shall be as follows:

a. 1″ meter . . . 16″

b. 2″ meter . . . 24″

c. other sizes provided upon request

6. All meters shall have a gate valve or ball valve on both sides of the meter.

7. Metered services which enter a building from two opposing sides shall have a double check valve assembly installed on the discharge side of the meter(s).

8. Commercial buildings, churches, schools and residential office buildings shall be serviced as follows:

a. Buildings of a single story, with one occupant, or a three thousand square foot main floor, shall have a two (2) inch service with meter size determined by the District Management.

b. All single story buildings over three thousand square feet containing one or more occupants or buildings having occupied basements and/or one and one half (1.5) stories in height or more, regardless of square footage, shall have a two (2) inch service with minimum size meter of one (1) inch. However, in each installation the District Management shall approve said installation prior to authorization of service.

9. Portions of the Uniform Plumbing Code will be used to assist in design of commercial services.

10. SADDLES

a. All services shall be made with the use of double strap saddles, using iron pipe thread only. Any exception must be approved by the District Management or District Engineer.

b. Dresser style 193 quick tap shall be used on asbestos concrete class 150 pipe with copper tubing. All services requiring a diameter of two (2) inches or larger shall have the following saddles:

1) Double strap saddles with wide band shall be used on steel, A.C., cast iron or P.V.C. pipe.

2) Services four (4) inches and larger may be made by using standard pipe tees or stainless-steel tapping sleeves with gate valves used in place of taps.

11. CORPORATION & CURB STOPS

a. Ball type compression corporation stops shall be used on one (1) inch taps. Mueller H-10013 male iron pipe (ball type) corporation stop shall be used for two (2) inch taps.

b. A two (2) inch ball type curb stop shall be used on two (2) inch services. One (1) inch compression ball type curb stop will be used on one (1) inch service.

12. PIPE

a. Two-hundred and fifty (250) PSI copper tube sized poly (CTS) or annealed copper Type K soft tubing only with a twelve (12) gauge copper insulated tracer wire shall be used on all one (1) inch services to the    property line.

b. Two (2) Inch Service Line Materials

i. CTS – Copper tube sized poly two-hundred and fifty (250) PSI with a twelve (12) gauge solid copper insulated tracer wire.

ii. Galvanized Iron Pipe – Two (2) inch galvanized may be used on two (2) inch services. Swing joints are required at corporation stop. Two (2) inch top taps will not be allowed. Swing joints shall consist of not less than three (3) each ninety (90) degree elbows. Fittings shall be 150 PSI rated galvanized malleable pipe.

13. Taps on steel, P.V.C.-C.I.P. or A.C. pipe will have no gooseneck exceeding thirty (30) degrees.

14. Side taps of two (2) inches shall be made at ninety (90) degree angles on steel P.V.C.-C.I.P. or A.C. pipe.

15. Curb boxes for one (1) inch services shall be “Tyler” type adjustable box with capabilities from forty-five (45) to sixty-six (66) inches and shall be placed no less than five (5) feet inside property line.

16. The curb stop shall be no deeper than eighty-four (84) inches.

17. A three (3) foot clear radius around the curb shall be maintained at all times.

III. WATER DISTRIBUTION

A. GENERAL

1. These specifications are intended for use in construction and as an aid to the licensed professional engineer in his design of facilities to become a part of the Whitworth Water District water system. All designs must be approved by Whitworth Water District prior to submitting to the Department of Health per WAC 246.190.220 and other State Department of Health rules and regulations pertaining to public water supplies.

2. All construction materials shall be new and unused and shall be approved by Whitworth Water District.

B. DESIGN FLOWS

1. Design flows will be the current flow required by either Spokane County Fire District No. 4 or Spokane County Fire District No. 9 plus maximum daily flow (see #5 below).

2. The District will review anticipated flow requirements for a new area to be served prior to final design of the system. Depending on the type of development, lot size, etc., requirements may vary and should be established before design of the system starts. Before the design phase starts, the District must verify that supply is available and anticipate the net effect of increased demand on the Whitworth system.

3. Minimum size of distribution mains shall be six (6) inches per Washington State Department of Health unless justified by hydraulic analysis per WAC 246.290.230.

4. Four-inch water lines are not allowed:

5. Main sizing shall be based on a minimum residual pressure of 20 psi during a fire event and a velocity of no greater than 8 feet per second at Peak Hourly Demand (PHD) plus required fire flow, and shall be determined by using 3500 gallons per day per connection times a peaking factor of 1.5.

6. RESIDUAL PRESSURE
Minimum of thirty (30) psi should be maintained at all curb stops during all design flows except fire flows.

IV. WATER MAINS

A. Mains are to installed across the front of the property, corner to corner. If a corner lot, the main shall be installed around the corner to the end of the property.

B. For cluster developments, the water main shall be extended to the far edge of the total property, not just to the last lot served.

C. Mains will be laid generally on the East and North side of streets, avenues, highways, and right-of-ways.

D. Where mains are extended into private property, easements for construction and perpetual maintenance shall be obtained prior to construction and acceptance from District. Easements shall be at least twenty (20) feet wide or as may be required by the District and shall specify no permanent buildings, fences or other structures be erected over water mains.

E. Permits from appropriate agencies are to be the responsibility of the party undertaking construction and shall be obtained prior to start of all work.

F. All mains shall have a minimum cover of four and one half (4.5) feet of earth cover. Where bottom of trench is found to have unstable soils, or is in rock conditions, an appropriate amount of material will be removed below the four and one half (4.5) feet, the depth being subject to District approval. Proper bedding material must also be used. Stones larger than one half (0.5) inch shall not be allowed within six (6) inches around any pipe.

G. All shaping, backfilling and compacting shall comply with American Public Works Association Standards. Ninety-five (95) percent compaction shall be required in traveled areas and ninety (90) percent compaction required in non-traveled areas. Compaction shall be as calculated by the Modified Proctor Method (ASTM-D-1557). It is noted that most water mains will be placed in Spokane County right-of-way and their requirements may supersede the above stated District requirements. Settling of the trench within a period of one (1) year after completion of the work shall be incontrovertible evidence of inadequate compaction and the developer shall be responsible for remedying the condition, including the replacement of surfacing materials, if necessary.

H. All workmanship shall be in compliance with all departments of all governmental agencies involved. Paving, cutting and replacement shall be in compliance with City, County and, and/or State road or street requirements.

I. Water mains shall be installed, under normal conditions, above all sanitary sewer lines. When deviations occur, the sewer pipe shall be sleeved with pressure water pipe in accordance with Washington Department of Health guidelines.

J. Water mains shall have a minimum clearance of fifteen (15) feet from all drain fields.

K. Pre-made thrust blocks will be used and are to be sized to resist design flaws and pressures. Ninety five (95%) percent compaction is required behind all thrust blocks.

L. No welding or torch cutting of pipe shall be allowed on coated pipe. All cutting shall be accomplished with a specific cutter.

M. Badly bent or stressed pipe shall be removed from the job site and replaced. All damaged wrapping shall be repaired with coatings approved by the District Management. In all cases the minimum accepted coating shall be Koppers Pankote “300” enamel or equivalent.

N. Lead caulked, flared, soldered or solvent weld joints shall not be allowed. All joints shall be made with A.W.W.A.- approved materials.

O. Number 12 solid copper insulated wire shall be installed in a continuous strand above all pipe. Wire shall be brought up inside all valve boxes. Wire shall also be run with all non-metallic service pipe. Water tight connectors will be used on all splices. 3M DBR-6 or equal.

P. All gaskets required between flanges shall be one-eighth (0.13) inch thick red rubber ring gaskets. They shall comply with A.W.W.A. specifications.

Q. All mains and their appurtenances shall be hydrostatically tested at 1.5 times the normal operating pressure or 150 psi, whichever is greater, for a period of one 1 hour. No leakage will be allowed and all defects shall be remedied and the line retested until it complies with the above requirements. Final testing shall be done in the presence of the District’s Inspector, Engineer, or authorized representative. All necessary equipment, gauges, tools, etc., for testing the installed piping shall be provided by the owner/developer.

R. Disinfection of all mains shall be accomplished according to A.W.W.A. specifications. Mains shall then be flushed and a satisfactory bacteriological sample must be achieved prior to placing mains in service for domestic consumption as per Spokane County Health District requirements. All samples will be taken by District personnel.

S. Any water main extension that has not been in service for longer than six (6) months will need to have new water samples taken. If the new water samples fail, re-chlorination of the water main will be necessary and done at the owner’s expense.

T. The safe disposal of chlorinated water will be the responsibility of the developer/contractor.

U. All cuttings, taps and other such work will only be performed with the specific tools manufactured for that purpose.

V. All fittings for underground installation shall be cement mortar lined ductile iron fittings (per A.W.W.A. #C-151).

W. Mega lugs will be used on all M.J. Connections.

X. Fittings used inside buildings and vaults will conform to the following:

1. Steel fittings used in pumping stations and vaults shall meet Federal specifications ASTM, A234, ASTMA 105.

2. Where standard A.W.W.A. approved ductile iron fittings are used, Federal Specifications shall also be met.

3. Coating used shall be Speedex Primer Finish 562-356628.

X. All connections to existing water mains will be done by District employees only.

V. TYPE OF PIPE

A. All distribution and transmission lines of six (6) inch, eight (8) inch, ten (10) inch and twelve (12) inch sizes shall be A.W.W.A. C900 PVC pipe and/or A.W.W.A. C-151 ductile iron pipe.

B. All mains larger than twelve (12) inches shall be ductile iron, in accordance with A.W.W.A. C-151.

C. Service lines from mains to either the meter or District shutoff shall be two-hundred and fifty (250) PSI copper tub